Project Details

  • Client : Telecommunications Company of Iran
  • Consultant: ATEC Consultants
  • Location: Tehran Province
  • Duration: 42 months
  • Completion: 1995
  • Execution cost: 6.8 billion Rials
  • Project usage: administrative, technical
  • Number of floors: 5 floors
  • Land Area: 29,500 m2
  • Landscaping Area: 19,572 m2
  • Project location: End of West 64 St, Kurdistan Junction, Kurdistan Highway, Tehran

This building as the center for telecommunications (internal and abroad) with a high capacity is parallel with Imam Square Telecommunication Center via three strings of optic cables. Thus, particularspecifications have been considered in the project’s architectural, structural, and mechanical design, the most important of which are:

  • Constructing more than 17,000 m2 false floor to facilitate cabling between various salons of machines and equipment.
  • More than 15 ventilator units for machinery salons, 3.3 megawatts emergency power generation plant.
  • Airtight windows and doors
  • Completely innovative system for installing façade stone tiles.

(In this building for the first time in Iran, façade stone tile has been installed in a dry and industrial method and without mortar). Restaurant and amphitheater have been included in this complex.