Project Details

  • Client: Saderat Bank of Iran
  • Consultant: Dahe Consulting Engineers
  • Location: Alborz Province- Karaj County
  • Duration: 48 months
  • Completion: 1996
  • Construction cost: 4.6 billion Rials
  • Project usage: administrative
  • Number of floors: 6 floors
  • Land Area: 7,945 m2
  • Total Area: 8,000 m2
  • Project location: Taleghani Junction, Karaj

The form of the building has created a favorable space for the entrance and use of dark color has created a special elegance.

The external façade is black granite and reflex glass, which the reflection of the sky and front buildings combines the building façade with existing environment.

The structure is made of reinforced concrete and enjoys state-of-the-art installation systems such as air conditioner. Wood has been used in internal architecture of ground floors, and stucco and paint in other floors.

Various floors of the building can be accessed through three stairways and three elevators.